# Lambda Kansas City

- Operator: Lambda
- Location: Kansas City, MO, United States (North America)
- Coordinates (approx.): 39.08, -94.6
- Type: AI campus (AI-focused)
- Status: Under construction
- Reported capacity: 100 MW (IT / critical load)
- Estimated grid power: 125 MW; IT load: 100 MW (PUE 1.25)
- Blackwell-equivalent GPUs (GB200 NVL72 basis): ~60k
- Notes: Retrofit of 2009 facility: 24 MW / 10k+ Blackwell Ultra initially (early 2026), room for 100 MW+
- Last checked: 2026-11-21

## Sources

- [Missouri DED — Lambda AI factory](https://ded.mo.gov/press-room/lambda-establish-ai-factory-facility-kansas-city)
- [Data Center Frontier — Lambda KC 100 MW+](https://www.datacenterfrontier.com/site-selection/article/55328500/land-expand-hyperscale-ai-factory-megascale)

Canonical page: https://atlas.kehai.co/f/lambda-kansas-city/ · Dataset: https://atlas.kehai.co/data.json