# Nebius Lappeenranta

- Operator: Nebius · Meta
- Location: Lappeenranta, Finland (Europe)
- Coordinates (approx.): 61.06, 28.19
- Type: AI campus (AI-focused)
- Status: Planned
- Reported capacity: 310 MW (IT / critical load)
- Estimated grid power: 388 MW; IT load: 310 MW (PUE 1.25)
- Blackwell-equivalent GPUs (GB200 NVL72 basis): ~186k
- Notes: $10B, 310 MW; follows Meta agreement
- Last checked: 2026-11-21

## Sources

- [Data Center Knowledge — Nebius $10B, 310 MW plan](https://www.datacenterknowledge.com/data-center-construction/nebius-s-10b-310mw-data-center-plan-signals-ai-infrastructure-shift)