DataVolt Oxagon
DataVolt
Under construction · AI campus · AI-focused
Grid power1.50 GW
IT load1.20 GW
Blackwell-equiv.720k
Reported figure: 1,500 MW as grid / total power. Converted with PUE 1.25 (AI campus default); GPU equivalents assume GB200 NVL72 racks (120 kW, 72 GPUs).
| Location | 🇸🇦 Oxagon, NEOM, Saudi Arabia |
|---|---|
| Region | Middle East & Africa |
| Notes | 1.5 GW campus; 360 MW first phase under construction since Aug 2026 (100 MW with Humain), due 2028 |
| Last checked | 2026-11-21 |
Sources
DCD — Humain breaks ground at Oxagonhttps://datacenterdynamics.com/en/news/humain-breaks-ground-on-neoms-oxagon-data-centerNEOM — Humain & DataVolthttps://www.neom.com/en-us/newsroom/HUMAIN-and-DataVolt-to-develop-AI-data-center-in-NEOM
Nearby in Saudi Arabia
| Facility | Location | Grid power |
|---|---|---|
| Humain Riyadh | Riyadh | 100 MW |
| Humain East Riyadh AI campus | East Riyadh | 6.00 GW |
| Humain Dammam | Dammam | 100 MW |