AWS Susquehanna (Cumulus)
Amazon (AWS)
Operating Β· Hyperscaler
Grid power960 MW
IT load800 MW
Blackwell-equiv.480k
Reported figure: 960 MW as grid / total power. Converted with PUE 1.20 (hyperscale data center default); GPU equivalents assume GB200 NVL72 racks (120 kW, 72 GPUs).
| Location | πΊπΈ Salem Township, PA, United States |
|---|---|
| Region | North America |
| Notes | Nuclear-adjacent campus bought from Talen |
| Last checked | 2026-11-21 |
Sources
Compiled from public reporting; not yet individually verified.
Nearby in United States
| Facility | Location | Grid power |
|---|---|---|
| CoreWeave Lancaster | Lancaster, PA | 125 MW |
| CoreWeave Kenilworth | Kenilworth, NJ | β |
| Nebius Vineland | Vineland, NJ | 375 MW |
| Equinix NY4/NY5 Secaucus | Secaucus, NJ | β |
| Equinix Ashburn DC campus | Ashburn, VA | β |
| Digital Realty Digital Dulles | Sterling, VA | β |