CloudBurst Central Texas
CloudBurst Data Centers
Under construction · AI campus · AI-focused
Grid power1.20 GW
IT load960 MW
Blackwell-equiv.576k
Reported figure: 1,200 MW as grid / total power. Converted with PUE 1.25 (AI campus default); GPU equivalents assume GB200 NVL72 racks (120 kW, 72 GPUs).
| Location | 🇺🇸 San Marcos, TX, United States |
|---|---|
| Region | North America |
| Notes | Three 400 MW phases |
| Last checked | 2026-11-21 |
Sources
Nearby in United States
| Facility | Location | Grid power |
|---|---|---|
| Microsoft San Antonio | San Antonio, TX | — |
| Stargate Milam County (SB Energy) | Milam County, TX | 1.20 GW |
| Google Midlothian | Midlothian, TX | 124 MW |
| Meta Fort Worth | Fort Worth, TX | — |
| Stargate Shackelford County (Vantage Frontier) | Shackelford County, TX | 1.40 GW |
| Stargate Abilene (Crusoe / Oracle) | Abilene, TX | 1.20 GW |