YTL Green Data Center Park
YTL · NVIDIA
Operating · AI campus · AI-focused
Grid power1.20 GW
IT load960 MW
Live IT today (est.)100 MW
Blackwell-equiv.576k
Reported figure: 1,200 MW as grid / total power. Converted with PUE 1.25 (AI campus default); GPU equivalents assume GB200 NVL72 racks (120 kW, 72 GPUs).
| Location | 🇲🇾 Kulai, Johor, Malaysia |
|---|---|
| Region | Asia Pacific |
| Notes | NVIDIA GB200 cluster live Oct 2025; park plan doubled from 600 MW to 1.2 GW (Jun 2026) |
| Last checked | 2026-11-21 |
Sources
NST — Kulai campus doubles to 1.2 GW (Jun 2026)https://www.nst.com.my/amp/business/corporate/2026/06/1472220/ytl-power-speeds-data-centre-expansion-kulai-campus-doubles-12gwEpoch AI — YTL Johorhttps://epoch.ai/data/ai-data-centers/directory/ytl-johor
Nearby in Malaysia
| Facility | Location | Grid power |
|---|---|---|
| Princeton Digital JH1 | Johor | — |
| Bridge DC Johor | Johor | — |
| Yondr Johor | Johor | 420 MW |
| AirTrunk JHB1 | Johor | 210 MW |
| DayOne Nusajaya | Iskandar Puteri, Johor | 662 MW |
| Equinix JH1 | Johor | — |