Colossus 1
SpaceXAI (xAI)
Operating · AI campus · AI-focused
Grid power300 MW
IT load240 MW
Blackwell-equiv.144k
Reported figure: 300 MW as grid / total power. Converted with PUE 1.25 (AI campus default); GPU equivalents assume GB200 NVL72 racks (120 kW, 72 GPUs).
| Location | 🇺🇸 Memphis, TN, United States |
|---|---|
| Region | North America |
| Notes | Converted Electrolux plant; built in 122 days |
| Last checked | 2026-11-21 |
Sources
Nearby in United States
| Facility | Location | Grid power |
|---|---|---|
| xAI Memphis Southaven power campus | Southaven, MS | — |
| Colossus 2 | Memphis, TN / Southaven, MS | 1.18 GW |
| AWS Madison County | Canton, MS | 1.20 GW |
| Meta Hyperion | Richland Parish, LA | 2.00 GW |
| Applied Digital Delta Forge 2 | Brookwood, AL | 262 MW |
| Applied Digital Delta Forge 1 | Boyce, LA | 430 MW |