DC AtlasOpen the interactive map →
DC Atlas / United States

Colossus 2

SpaceXAI (xAI)
Operating · AI campus · AI-focused
Grid power1.18 GW
IT load946 MW
Live IT today (est.)946 MW
Blackwell-equiv.568k

Reported figure: 946 MW as IT / critical load. Converted with PUE 1.25 (AI campus default); GPU equivalents assume GB200 NVL72 racks (120 kW, 72 GPUs).

Location🇺🇸 Memphis, TN / Southaven, MS, United States
RegionNorth America
Notes~946 MW IT per S-1-based estimate; expansion toward ~2 GW
Last checked2026-11-21
See it on the map →

Sources

Epoch AI — Largest AI data centers by power (Nov 2026)https://epoch.ai/graphs/largest-ai-data-centers-by-power-capacityEpoch AI — Colossus 2https://epoch.ai/data/ai-data-centers/directory/colossus-2

Nearby in United States

FacilityLocationGrid power
xAI Memphis Southaven power campusSouthaven, MS—
Colossus 1Memphis, TN300 MW
AWS Madison CountyCanton, MS1.20 GW
Meta HyperionRichland Parish, LA2.00 GW
Applied Digital Delta Forge 2Brookwood, AL262 MW
Applied Digital Delta Forge 1Boyce, LA430 MW